$10k - $80k

Please note the 1 July 2024 CPRs implement a range of changes that may not be reflected throughout all currently available guidance materials. The Department of Finance is in the process of updating all guidance materials. Until this process is complete, references to CPR paragraph numbers and footnotes may be inaccurate.

If you have come to this page directly, please go to the BuyRight home page. This contains conditions that you need to first consider when conducting your procurement.

Key policies that apply to procurements in this value range are:

Start at step C.1 below and follow the entire process.

C.1. You May Wish To Check for an Existing Standing Offer Arrangement (Panel)

Standing offer arrangements (panels) are set up by entities for frequently sourced goods or services. To maximise competition, officials should, where possible, approach multiple suppliers on a standing offer.

The benefits in using a standing offer are:

  • a competitive process has already been undertaken and suitable suppliers have been identified
  • contract terms and rates have already been agreed
  • entities may be able to use panels that have been set up by other entities which provide efficiencies to both purchaser and supplier.

Note: How do I find a standing offer (panel)?

  • Standing offers are listed on AusTender.
  • All standing offer arrangements are listed under a Standing Offer Notice (SON). The SON will show you approved suppliers and provide some details of the panel.
  • Check to see whether your entity is able to use the standing offer- there is a section on the SON that notes who is able to use the standing offer arrangement.
  • If the standing offer also has a panel ID then it is managed and accessible from Dynamic Sourcing for Panels (DS4P) tool within AusTender.
  • If your entity is approved to use that standing offer, documentation can be accessed from the tool once you register in the system as a government buyer. Otherwise you will need to contact the panel manager via the contact details for any documentation.

► Review standing offer arrangements to see if there is a standing offer that suits your requirements.

If you find a standing offer, do not continue with this $10k - $80k process. Follow the Using an Existing Standing Offer process.

C.2. Plan your Procurement

You will need to identify who can provide the required goods or services.

Consider:

  • Are there many suppliers in the market or is it quite limited?
  • Are these goods/services available off the shelf or do they require customisation?

Thinking about these things will assist you in defining your requirements and in deciding how many suppliers to approach.

Investigate the market – use the internet to look for potential suppliers and/or look at AusTender to find similar procurements.

Define your requirements in a way that can be easily understood by potential suppliers. If your requirements are more complex, such as:

  • you are not sure who can provide the goods/services
  • you are not sure exactly what the service involves or what is the best approach
  • you are not sure what the suppliers can offer
  • consider using terms that specify performance and/or functional requirements. Try to define the steps or processes that you think would be part of the service. This will help suppliers to understand what you think is involved.

Decide who you would like to approach.

For procurements up to $80k you have the flexibility to directly approach one or several potential suppliers. Keeping in mind that your procurement process (and the time and effort required) should be commensurate with the scale and scope of the business requirement, you will need to justify that the approach and expected outcome represents value for money.

If your requirement is simple, you may decide to approach only one supplier. If you are not familiar with either the market or the requirement, you may decide to go out to more suppliers to test what might be available.

If your requirement is more complex, as described above, you may find the following helpful:

If your requirement is very complex or has a high-risk profile, you may wish to use the $80k-$200k process that provides a more rigourous process and further considerations, noting that you are still not required to approached the market through open tender even though following the more complex process.

Note:

One of the considerations used to assess value for money is that the procurement process should: “use public resources in an efficient, effective, economical and ethical manner that is not inconsistent with the policies of the Commonwealth.”

Note: Sustainable Procurement

Recognising the Australian Government’s commitment to sustainable procurement practices, entities are required to consider the Australian Government’s Sustainable Procurement Guide when undertaking procurements, including in the assessment of value for money, where there is opportunity for sustainability or use of recycled content.

C.3. Obtain Delegate Endorsement to Approach the Market (ATM)

Before you go out to market you need to gain your delegate’s agreement that the proposed approach is right for this requirement.

► Discuss your procurement with the delegate; confirm the scope, that funding is available, and details of the approach to market.

► Record in-principle approval to proceed.

The delegate is likely to consider the following:
  • expected cost and whether unallocated funds are available.
  • the risk profile and risk management strategies if required.
  • any potential conflicts of Interest (see APSC policy).
  • how you are going to approach the market.

The CCS Procurement Plan provides details of other potential issues which may be useful.

C.4. Obtain Quote(s)

When going out to potential suppliers, you MUST ensure that your approach is consistent and equitable to all potential suppliers.

► Use the approach to market that the delegate agreed to in Step 3: Obtain delegate endorsement to approach the market (ATM).

► If approaching multiple potential suppliers ensure you provide equal conditions and information (e.g. create an email template to send to each supplier or script your phone calls). For email ATMs it is appropriate to attach the CCS ATM terms (see RMG No. 420). Alternatively, you may choose to use AusTender to undertake a limited approach.

► If you require a purchase order or contract, attach the mandated Commonwealth terms (purchase order or contract terms) when seeking a quote. Not all requirements will need a formal approach to market and/or contract (see RMG No. 420). This is dependent on the complexity and risk profile of your procurement.

► If you receive questions from potential suppliers while out to quote, answer them promptly. If any questions result in new information relating to the scope of the procurement you will need to provide the question and answer to all suppliers, without identifying the source of the question.

Note

For simple procurements verbal or email quote(s) are usually sufficient.
You should not retrospectively apply contract terms if you did not specify them in the approach to market.

C.5. Evaluate Supplier Responses

In order to decide which quote to accept, you will need to evaluate each of the supplier responses and make an assessment about which one represents the best value for money (VFM) to the Commonwealth. VFM is a combination of all relevant financial and non-financial costs and the anticipated benefits of each response.

If only one quote is received:

► evaluate whether the quote meets your requirement and is priced appropriately. This will form the basis of your VFM justification.

If multiple quotes are received, consider:

► which quote best meets your requirement (e.g. quality, fit for purpose, delivery times etc.).

► which quote represents the best price relative to their ability to meet your requirements (value for money of VFM).

► if you included evaluation criteria when you requested your quote then you MUST evaluate all responses against those criteria (the criteria for evaluating responses is clearly set out in the Commonwealth ATM Terms Clause A.B.5 – Evaluation.

► you may want to use the CCS Tender Evaluation Report to guide your process.

If no quotations were received or do not represent VFM, you will need to refine your procurement requirements and go back to Step 2: Plan your procurement.

Note: Sustainable Procurement

Recognising the Australian Government’s commitment to sustainable procurement practices, entities are required to consider the Australian Government’s Sustainable Procurement Guide when undertaking procurements, including in the assessment of value for money, where there is opportunity for sustainability or use of recycled content.

C.6. Using Supplier Terms and Conditions

In accordance with RMG No. 420 you MUST use CCS Contract Terms unless you meet any of the conditions in RMG No. 420 Part 2. 

Sometimes a supplier’s terms will include a ‘contingent liabilities’ clause. A contingent liability is a potential liability that may occur depending on the outcome of an uncertain future event (see RMG No. 414). These are often found with venue hire, software licensing, product warranty and when you click on the ‘I agree’ to online terms and conditions.

► Check the supplier’s terms and conditions for contingent liabilities. If this clause is included, or you are unsure, seek advice from your central procurement area or in-house legal advisors.

► Seek written delegate approval for any contingent liabilities. This approval may be combined with next Step 7: Obtain Delegate Approval under PGPA Section 23.

Note

If using a supplier’s contract, you still need to comply with the payment terms set out in Resource Management Guide (RMG) No. 417 – Supplier Pay on Time or Pay Interest policy, which require maximum payment terms of 20 days or 5 days if using e-invoicing. If required, contracts may stipulate shorter payment terms.

C.7. Obtain Delegate Approval under PGPA Section 23

Once you have completed your evaluation and before entering an agreement, you MUST seek approval under section 23 of the Public Governance Performance and Accountability Act 2013 (PGPA Act).

► Seek the delegate’s agreement to the recommendations resulting from Step 5: Evaluate Supplier Responses.

► Draft your approval minute (if you have used the CCS Evaluation Report this will generate automatically). Alternatively, this may be in the form of an email.

► Prepare a draft purchase order or contract if required. If a formal contract is required you MUST use the Commonwealth Contracting Suite (CCS) unless your procurement meets any of the conditions outlined in RMG No. 420 part 2.

► Provide approval email or minute to delegate for approval. Include the draft purchase order or contract if applicable.

Note

When does the contract get signed?

The delegate should not sign the contract at this point. The supplier should sign the contract FIRST but not before PGPA Section 23 approval is granted.

C.8. Formalise Order

Once relevant approvals have been obtained, you can finalise the placing of your order. This may be done by one of the following:

► accept the supplier's quote - this may be done verbally or by email (if done verbally you should record this in some form).

OR

► place a purchase order - the supplier is then required to accept the purchase order (an email will be sufficient). Ensure that you attach a copy of the Commonwealth Purchase Order Terms.

OR

► send a copy of the contract to the supplier - the supplier is required to return a signed copy of the contract (either physically or electronically). The Commonwealth is then required to sign and return a signed copy of the contract to the supplier.

► after the contract (including purchase orders or quote acceptance) has been formalised, enter this procurement into your entity's Financial Management Information System (FMIS). (You may also be required to submit relevant documentation).

► entities MUST report contracts (including purchase orders or quote acceptance) on AusTender within 42 days of entering into a contract (see CPRs 7.18). Your FMIS may facilitate this reporting or you may have to do this manually. Check with your CFO or your central procurement area.

Note: Mandatory Use of the Commonwealth Contracting Suite (CCS) contract.

Use of the CCS contract is mandatory for procurements under $200k unless your procurement meets one of the exceptions listed in Part 2 of the Resource Management Guide (RMG) No. 420 - Mandatory use of the Commonwealth Contracting Suite for procurement under $200,000.

You will need to assess your procurement to see if other contracting vehicles such as acceptance of quote, use of purchase order or another form of contract are appropriate in accordance with the RMG 420, otherwise you will need to use a CCS contract.

For further advice contact your central procurement area.

Note: Payment Terms

If you are not using a CCS contract or the Commonwealth Purchase Order terms, Resource Management Guide (RMG) No. 417 – Supplier Pay on Time or Pay Interest policy still applies. RMG No. 417 applies to most Non-corporate Commonwealth Entity (NCE) procurements “even if a written contract or approach to market fails to include clauses that reflect this policy, or if no written contract exists between the NCE and the supplier”.

This means that regardless of the type of contract you are using, you need to comply with the payment terms set out in RMG No. 417, which require maximum payment terms of 20 days or 5 days if using e-invoicing. If required, contracts may stipulate shorter payment terms.

Note: Sustainable Procurement

Recognising the Australian Government’s commitment to sustainable procurement practices, entities are required to consider the Australian Government’s Sustainable Procurement Guide when undertaking procurements.

If the successful supplier has stated sustainability commitments or targets in their quote and these formed part of the value for money assessment then you will need to include these in your contract or purchase order. Any commitments or targets will need to be measurable and the supplier’s performance against these measures will need to be monitored.

C.9. Advise unsuccessful suppliers

Once the procurement has been finalised, you MUST notify any unsuccessful suppliers that provided quotes.

► You MUST notify the unsuccessful supplier(s). Notifying unsuccessful supplier(s) in writing (an email may be sufficient) provides a record of notification.

► You MUST offer all suppliers (including the successful supplier) the opportunity to receive feedback on their offer.

Note:

When conducting a de-brief give constructive, honest and evidence based feedback.  The supplier will be interested in the strengths and weaknesses of their proposal in order to improve future submissions.

It is important that you do not include comparative assessments or details of other tenders, particularly any pricing information.

C.10. File documents

You are required to retain all relevant documents in accordance with the Archives Act 1983. Relevant documents include any documents that record decisions and/or approvals, including those with signatures.

► File documents in accordance with your entity's records management practices.

► Manage the contract. More information can be found in the Australian Government Contract Management Guide on the Department of Finance website.